Construction Progress Update
Friday, July 25, 2016
General Project Information
1. Construction began on Monday, April 25, 2016
2. Contract Day 91 of 150
NORTH AREA UPDATE
(Travers Lane, Marston Lane, Cummings Lane, Hutchison Road, Vardon Lane, Latimer Lane)
Work Completed to Date:
1. All work is 100% complete
Restoration Notes:
1. Many areas where grass was restored will settle after rain events. The contractor is aware of this and will come back to fix all these
settled areas in the early fall.
SOUTH AREA UPDATE
(Tina Lane, Markey Lane, Thomas Court, Pinehurst Lane)
1. Water main work in the south area is scheduled to begin the week of August 1, 2016
Please call Public Works at 708-957-4100 if you have any questions or need additional information.